Project Plan Submission Documentation for Projects with a FEED or FEED Equivalent Study, or Construction Ready or Under Construction
Natural Resources Canada (NRCan) assesses project plan submissions that include one or more of the following document packages, based on the level of maturity of the project, i.e., FEED to construction:
- A Front-End Engineering and Design (FEED) study.
- A FEED equivalent engineering study (i.e., an engineering package at the Front-End Loading 3 stage (FEL-3).
- A ‘construction ready’ documentation package with a complete detailed engineering design package supported by all drawings issued for construction.
If the project is at the design stage or has not yet reached a Final Investment Decision (FID), a FEED study or a FEED equivalent engineering study must be completed. A FEED package would include documents #1 to 10 from the table below.
If the project is at the construction stage, instead of the FEED package, relevant detailed engineering documents aligned with the current project stage must be provided (e.g., detailed engineering documents required for construction).
All documents that will be required in the project plan submission form, including the above described documents, are listed in the following table. As part of the project plan submission form, you need to include the following, as applicable:
- #1-16 if the captured carbon dioxide (CO2) is both stored in dedicated geological storage, in Canada or the United States, and sequestered in concrete using a qualified concrete storage process.
- #1-13, 15, and 16 if the captured CO2 is only being stored in dedicated geological storage, in Canada or the United States.
- #1-12, and 14-16 if the captured CO2 is only sequestered in concrete using a qualified concrete storage process.
Before the ITC is claimed, it is required that the final engineering design package for the project be reviewed by NRCan to verify the final CCUS property list.
For any submitted project plan, an Initial Project Evaluation will be issued by NRCan based on the documentation provided in the project plan submission. Project updates and reporting of material changes may be required. See Your reporting responsibilities and Project changes and impacts
Document | Attachment | Description |
---|---|---|
1 | Design basis/ philosophy or detailed engineering design |
A complete record of the fundamental principles and decision-making process behind critical design choices to fulfill the CCUS project requirements, as applicable to the type of project, including, but not limited to:
|
2 | Process flow diagrams (PFDs) |
Standard engineering diagram(s) labeled according to standard engineering practices showing all relevant elements, as applicable to the type of project, including, but not limited to:
PFDs must clearly indicate process and ownership boundaries, if applicable, and ensure all equipment labels/IDs are consistent across all engineering documents. |
3 | Utility flow diagrams (UFDs) |
Standard engineering diagram(s) labeled according to standard engineering practices, showing, as applicable to the type of project, but not limited to:
UFDs must clearly indicate process and, if applicable, ownership boundaries, and ensure all equipment labels/IDs are consistent across all engineering documents. |
4 | Piping and instrumentation diagrams (P&IDs) |
Standard engineering P&ID diagrams labelled with standard engineering symbols and notation, showing, as applicable to the type of project, but not limited to:
P&IDs must clearly indicate process and, if applicable, ownership boundaries and ensure all equipment labels/IDs are consistent across all engineering documents.
|
5 | Major equipment package list |
Major equipment package list, including, as applicable to the type of project, but not limited to:
|
6 | Energy and material balances |
A complete energy and material balance for all streams referenced in the PFDs and UFDs, including, but not limited to:
|
7 | Electrical one-line diagrams |
Standard electrical one-line representative drawings of the electric power system of the planned CCUS process, as applicable to the project, including, but not limited to:
Electrical one-line diagrams must clearly indicate process and, if applicable, ownership boundaries, as well as boundaries between existing and planned CCUS and dual-use equipment. Ensure all equipment labels/IDs are consistent across all engineering documents. |
8 | Site plans |
Standard civil engineering drawings showing the location and plans for the construction of required civil work, including, but not limited to:
|
9 | Itemized capital cost assessment |
An itemized Class 3 (for projects at FEED stage) or Class 1 (for projects under construction) list of capital costs including, but not limited to:
Refer to the Association for the Advancement of Cost Engineering (AACE) Class system for cost estimation classification. |
10 | Level 3 schedule |
A project summary level 3 schedule that spans the entire project duration and includes all, but not limited to:
|
11 | CCUS tax credit property list |
A completed CCUS Tax Credit Property List to be provided with the project plan submission form. An itemized property list to (or already) be purchased, constructed, and installed for the CCUS and dual-use facilities, including:
Enter all equipment, buildings, and structures from engineering drawings that needs to be considered for the CCUS ITC in appropriate tab(s) of the CCUS Tax Credit Property List. For each item, clearly indicate:
Ensure all references are consistent across drawings, tables and lists. For each dual-use equipment, building or structure, provide the appropriate ID and, as applicable, CCUS factor (dual-use factor). |
12 | Dual-use equipment calculations |
Provide an itemized list of all dual-use equipment, buildings, and structures to be purchased, constructed, and installed for dual-use facilities. Submit a document showing the detailed calculations of the reported dual-use and/or CCUS factors for each dual-use property (equipment, building or structure). Each dual-use property must be clearly identified by its ID, ensuring consistency across all documents.
Details of these calculations are available in NRCan's CCUS ITC Technical Guidance Document. |
13 | Pore space allocation |
Statements of fact, to be included within the project plan submission, that clearly:
|
14 | Concrete storage |
Statements of fact, to be included within the project plan submission, must clearly:
Additional proofs may be required by CRA, see After you claim. |
15 | Letters of intent or agreements |
For projects at FEED stage, statements of fact, to be included within the project plan submission, clearly confirming that:
For projects under construction, relevant documents signed by all parties involved in the CCUS value chain outlining the agreement for the CCUS Tax Credit claimants to:
Provide captured CO2 for transport and/or eligible use. |
16 | CO2 eligibility template |
Complete CO2 Eligibility Template (available in the submission portal), indicating the quantity of captured CO2 that the project is expected to support for storage or use (include eligible use and ineligible use), in each calendar year over its total CCUS project review period. Refer to CCUS ITC legislation for definitions of “eligible use” and “ineligible use”. |
Boundary Delineation
Refer to NRCan's CCUS ITC Technical Guidance Document for examples.
Process boundaries
- between CCUS and non-CCUS equipment identified by dashed red lines that are distinct from any other labelling on the engineering diagram.
- between eligible dual-use equipment and non-CCUS or CCUS equipment identified by dashed green lines that are distinct from any other labelling on the engineering diagram.
Ownership boundaries
- representing different ownership of the process equipment outlined by dotted blue lines that are distinct from any other labelling on the engineering diagram.
Page details
- Date modified: