What is the Towerbirch Pipeline Expansion Project?
On 2 September 2015, the National Energy Board (Board or NEB) received NOVA Gas Transmission Ltd.’s (NGTL) Application for approvals to construct and operate pipeline facilities that will be part of the existing NGTL System. The proposed Towerbirch Expansion Project (Project) includes:
- construction of 87 km of new gas pipelines and associated facilities in northwest Alberta and northeast British Columbia,
- Tower Lake Section (32 km of 762 mm OD pipe)
- Groundbirch Mainline Loop (55 km of 914 mm OD pipe)
- additional associated facilities, including meter stations, valve sites and pipeline tie-ins.
Project map
This map provides an overview of the Towerbirch Expansion Project.
Links to additional information
Learn more about the NGTL Towerbirch Expansion Project:
- The Government of Canada’s Interim Approach for the Review of Existing Projects
- Project proponent’s website: TransCanada
- Recommendations and Conditions of the National Energy Board for the NGTL Towerbirch Expansion Project
- Environment and Climate Change Canada’s assessment of upstream greenhouse gas emissions: Review of Related Upstream Greenhouse Gas Emissions Estimates